District Planning - The Government of Maharashtra is among the first few states to adopt the principle of decentralized planning.  In this process the district have the direction to give priorities among the various developmental schemes within the outlays provided to district. For this purpose, the schemes and programmes in the state plan are classified as state level schemes ( planed and funded at state level) State pool schemes, ( District level schemes, but planed and funded from the state pool fund.)  And regular district level schemes draft district plans are prepared by DPC'S & forwarded to government.  The minister (finance & planning) held  meetings  with the representatives of the DPC'S  so for as non tribal  plans are  concerned, minister treble welfare  so far  T.S.P. is concerned & minister (Social welfare ) so far as special component plans is concerned at the State level.  On the  basis of  these discussions  the district plan finalized and  monitored by DPC's.

Statement Of outlays, grant received and actual expenditure for district level schemes in the annual plan,  from the Year 1999-2000  to 2005-2006.                                                                                                                                                                                             

                                                                                                 Rs Lakhs

Sr No

Name of the schemes

outlays

Grant Received

Actual Expenditure

1

2

3

4

5

 

 

1999-2000

 

 

1

District level schemes (Non Treble)

1787.23

1783.03

1912.193

2

Special component plan(S.C.P.)

705.39

674.61

  668.63

3

O.T.S.P

49.09

107.96

106.99

 

Total

 2541.71

2565.60

2688.55

 

 

2000-2001

 

 

1

District level schemes (Non Tribal)

1436.00

1199.53

1230.02

2

Special component plan(S.C.P.)

821.00

679.17

671.92

3

O.T.S.P

49.00

66.97

53.47

 

Total

2306.00

1945.67

1955.41

 

 

2001-2002

 

 

 

1

District level schemes (Non Tribal)

1436.00

1220.68

1197.29

 

2

Special component plan ( S.C.P.)

821.00

            629.18

616.34

 

3

O.T.S.P.

50.00

30.35

20.18

 

 

Total

2307.00

1880.21

1833.81

 

 

 

2002-2003

 

 

 

1

District level Schemes (Non tribal)

1399.00

1049.42

1027.65

 

2

Special Component plan (S.C.P.)

790.00

578.65

557.24

 

3

O.T.S.P.

45.39

16.62

9.87

 

 

Total

2234.39

1644.69

1594.76

 

 

 

2003-2004

 

 

 

1

District level schemes (Non tribal

1399.00

855.34

847.25

 

2

Special component plan (S.C.P.)

790.00

537.73

538.94

 

3

O.T.S.P.

45.39

31.89

29.31

 

 

Total

2234.39

1424.96

1415.50

 

 

 

2004-2005

 

 

 

1

District level schemes (Non tribal)

1399.00

683.82

671.04

 

2

Special component plan (S.C.P.)

795.00

566.33

565.03

 

3

O.T.S.P.

31.02

11.24

10.82

 

 

Total

2225.02

1261.39

1246.89

 

 

 

2005-2006

 

Up to June 05

 

1

District level schemes (Non tribal)

1305.89

158.71

35.42

 

2

Special component plan (S.C.P.)

197.50

--

--

 

3

O.T.S.P.

32.32

--

--

 

 

Total

2175.71

158.71

35.42

 

   


   Removal of Regional Imbalance

 

Government had appointed a Fact Finding Committee (FFC) in August 1983 under the Chairmanship of Dr. V.M. Dandekar for studying the problems of imbalance between different region of the State to identify the regional backlog on the basis of such a study and to suggest measures for the removal of the regional backlog including long term measures to avoid such regional imbalance in the future. The report of the Fact Finding Committee was made available to Govt. in June 1984. The Fact Finding Committee had identified backlog of Rs. 3186.78 Crores.

 

The process of removal of backlog identified by the FFC was started from the year 18985-86 by giving special outlays. After the establishment of the Development boards to workout the revised backlog of the different regions of the State. Hon’ble Governor had setup ‘Indicators & Backlog Committee’ in 1995. The committee submitted its report in July 1997. The Government has accepted the report in principle. The committee worked out fresh backlog of Rs. 15355 Crores. Considering the development that took place till March 94-95 as the ‘Indicators & Backlog Committee’ workout fresh backlog. But the physical backlog calculated by the ‘Indicators & Backlog Committee’ was not acceptable to some of the departments. Hon’ble Governor therefore reconstituted the ‘Indicators & Backlog Committee’ . The reconstituted backlog committee finalised the backlog at Rs. 14006.77 Crore as on 31st March 1994.

 

          Sector wise final cost of backlog identified by ‘Indicators & Backlog Committee’

District Parbhani (Including Hingoli)

Sr. No.

Sector

Rs. In crore

1

Irrigation

54.00

2

Road

128.69

3

Gen. Education

9.70

4

Tech. Education

12.11

5

Health Services

72.36

6

Water Supply

25.70

7

Land Development Soil & Water Cons.

29.92

8

Veterinary sector

0.29

9

Electrification of Pumps

41.15

 

Total

373.87

 

 

Sector wise Expenditure incurred under backlog from the year 1985-86 to 2004-05

 

Dist. Parbhani

Sr. No.

Sector

Actual Expenditure (Rs. In Lakhs)

1985-86 to 2000-2001

2001-02

2002-03

2003-04

2004-05

1

2

3

4

5

6

7

1

Roads

12246.42

105.18

85.12

312.00

7.03

2

Electrification

1420.41

214.02

2483.78